Capital Costs

The Project’s total projected capital cost is summarized in Table 3.

Table 3: Project Capital Cost Estimates ($US Millions)
Graphite Creek Mine
$  43
Processing Plant
$158
Infrastructure
$  32
          Sub-total Graphite Creek
$233
Manufacturing Plant
$130

Project Total

$363