Capital Costs

The Project’s capital costs, estimated in the PEA, are summarized in Table 6.

Table 6: Project PEA Capital Cost Estimates ($US Millions)
Graphite Creek Mine
$  43
Processing Plant
$158
Infrastructure
$  32
          Sub-total Graphite Creek
$233
Manufacturing Plant
$130

Project Total

$363
Sign up for the latest news and updates
X